Commercial Post-Frame Timeline: Lakewood Case Study

6 min read
Commercial Post-Frame Timeline: Lakewood Case Study - Article featured image

When it comes to commercial construction in Western Washington, post-frame building methods offer exceptional value, durability, and versatility. At Probuilt Metal Buildings, we recently completed a commercial project in Lakewood that showcases how post-frame construction can efficiently meet the needs of business owners while navigating the unique challenges of our Pacific Northwest climate and local regulations.

This timeline walks you through each phase of a typical post-frame commercial project, offering insights into our process and what potential clients can expect when working with our team.

Phase 1: Initial Consultation and Conceptualization (Weeks 1-2)

Every successful project begins with a thorough understanding of the client's needs. During our initial meetings with the Lakewood business owner, we:

  • Conducted detailed interviews to understand business operations and specific building requirements
  • Evaluated the property site for topography, drainage, access, and utilities
  • Discussed budget parameters and timeline expectations
  • Presented preliminary design concepts and material options
  • Explained the advantages of post-frame construction for their specific application

This critical planning stage established the foundation for the entire project. Our experienced team took the time to fully understand not just what the client wanted, but why they needed it, allowing us to suggest design modifications that would enhance functionality while controlling costs.

Phase 2: Design Development and Engineering (Weeks 3-6)

Once we established a clear vision for the project, our design team went to work creating detailed plans:

  • Developed architectural drawings with precise dimensions and specifications
  • Worked with structural engineers to ensure designs met or exceeded local building codes
  • Created 3D renderings to help the client visualize the finished building
  • Selected appropriate materials optimized for our Pacific Northwest climate
  • Calculated precise material quantities and construction timelines

During this phase, we maintained regular communication with the client, presenting design iterations and making adjustments based on feedback. Our engineers paid particular attention to snow load requirements, wind resistance, and moisture management—critical considerations for commercial buildings in the Lakewood area.

Phase 3: Permitting and Pre-Construction Planning (Weeks 7-12)

Pierce County and the City of Lakewood have specific requirements for commercial construction. Our team handled all aspects of the permitting process:

  • Prepared and submitted comprehensive permit applications to Lakewood officials
  • Scheduled and attended necessary inspections and review meetings
  • Made required adjustments to plans as needed to satisfy local building codes
  • Secured all necessary approvals and permits before breaking ground
  • Developed detailed construction schedules and coordinated with subcontractors

This phase often requires patience, but our established relationships with local building departments helped streamline the process. While waiting for final approvals, we finalized material orders, scheduled deliveries, and prepared the construction site plan to ensure a smooth transition to the building phase.

Phase 4: Site Preparation and Foundation Work (Weeks 13-15)

With permits in hand, physical work began on the Lakewood site:

  • Cleared and graded the building site to ensure proper drainage
  • Installed temporary utilities and site access points
  • Excavated for footings and prepared for concrete work
  • Poured concrete footings and foundation according to engineered specifications
  • Allowed proper curing time while preparing for the next construction phase

Despite typical Pacific Northwest winter weather conditions, our experienced team maintained the schedule by implementing weatherproofing measures and carefully planning concrete pours around forecasted rain. Our high-quality site preparation created a solid foundation for the post-frame structure.

Phase 5: Post-Frame Construction and Structural Framing (Weeks 16-19)

This phase showcased the speed and efficiency of post-frame construction methods:

  • Installed treated posts secured to concrete foundations
  • Erected primary structural framework including trusses and purlins
  • Installed roof structure and metal roofing system
  • Completed exterior wall framing and sheathing
  • Added doors, windows, and exterior trim

The client was particularly impressed with how quickly the building took shape during this phase. The post-frame method allowed our crew to erect the main structure in significantly less time than conventional construction would require, even with occasional weather delays.

Phase 6: Exterior Finishing and Weatherproofing (Weeks 20-22)

With the structure in place, we focused on creating a weather-tight building envelope:

  • Installed high-quality metal siding with proper insulation
  • Applied commercial-grade seamless gutters and downspouts
  • Completed exterior trim work and caulking
  • Installed energy-efficient commercial doors and windows
  • Added exterior lighting fixtures and signage mounts

Our attention to detail during this phase ensured the building would remain weathertight and energy-efficient through years of Pacific Northwest weather. The metal exterior materials were selected specifically for their durability and minimal maintenance requirements in our climate.

Phase 7: Interior Construction and Finishing (Weeks 23-28)

With the building secure from the elements, interior work proceeded efficiently:

  • Completed electrical, plumbing, and HVAC rough-ins
  • Installed insulation and vapor barriers
  • Constructed interior walls and partitions according to the floor plan
  • Installed ceilings, flooring, and interior trim
  • Completed final electrical, plumbing, and mechanical installations

Our team coordinated closely with specialized subcontractors during this phase, ensuring all systems were installed correctly and according to code. The open-span design made possible by post-frame construction gave the client maximum flexibility for interior layout.

Phase 8: Final Inspections and Project Completion (Weeks 29-30)

Before turning the keys over to the client, we ensured every detail was perfect:

  • Conducted thorough quality control inspections
  • Scheduled and passed all required municipal inspections
  • Made final adjustments and touch-ups as needed
  • Completed site cleanup and landscaping restoration
  • Walked through the completed building with the client for final approval

Our commercial building in Lakewood received final approval right on schedule, allowing the business owner to begin operations without costly delays. The project demonstrated the perfect combination of post-frame efficiency and commercial-grade quality.

Why This Timeline Matters

This 30-week timeline from concept to completion represents a typical commercial post-frame project in Pierce County. While every project is unique, this case study demonstrates how post-frame construction can deliver commercial-quality buildings in significantly less time than traditional construction methods.

The Lakewood business owner particularly appreciated:

  • The cost savings of approximately 30% compared to conventional construction
  • The energy efficiency provided by our insulation package
  • The minimal maintenance requirements of metal roofing and siding
  • The flexible interior space with no load-bearing walls to limit future reconfiguration
  • The strength and durability of post-frame construction in our climate

At Probuilt Metal Buildings, we specialize in delivering high-quality post-frame commercial structures throughout Western Washington. Our proven process ensures your project proceeds smoothly from initial concept to final inspection, with clear communication at every stage.

Contact us today to discuss how we can help turn your commercial building needs into reality with the efficiency, durability, and value that only post-frame construction can provide.

Share this article

Help others discover this article

Share this article with your network to help spread the word.

Ready to Start Your Project?

Get a free quote on your metal building project. No obligation, no pressure.