Post-Frame Building Project Planning Guide

7 min read
Post-Frame Building Project Planning Guide - Article featured image

When David started planning his 40x60 workshop in Lakewood, he thought the process would be straightforward: find a contractor, get a quote, and start building. Six months later, after dealing with three different contractors, permit delays, and budget overruns, he wished he had known what he was getting into.

David's story isn't uncommon. Over 15 years, we've seen dozens of projects go sideways due to poor planning. But we've also guided hundreds of successful projects from concept to completion. Here's the step-by-step process that ensures your post-frame building project succeeds.

Phase 1: Project Definition (Week 1-2)

The Puyallup Auto Shop Success Story

The Challenge: A mechanic needed a 30x40 auto repair shop but had never built anything before. His initial "requirements" were simply "somewhere to fix cars."

Our Planning Process:

  • Function analysis: How many bays? What equipment? Customer area?
  • Future planning: Growth projections for 5-10 years
  • Workflow design: Traffic patterns for vehicles and customers
  • Code requirements: Commercial auto repair regulations
  • Budget realities: Total project cost vs. available financing

Results: Clear project scope that prevented costly changes during construction. Final building exceeded expectations while staying within budget.

Essential Planning Questions

Before contacting any contractor, answer these questions:

Primary Function:

  • What will happen in this building daily?
  • What equipment or vehicles must it accommodate?
  • How many people will use it simultaneously?
  • Will functions change seasonally?

Size Requirements:

  • Minimum dimensions for current needs
  • Ideal dimensions for optimal function
  • Maximum size property/budget allows
  • Expansion possibilities

Performance Requirements:

  • Insulation needs (climate control vs. basic weather protection)
  • Electrical requirements (basic vs. heavy equipment)
  • Plumbing needs (none vs. basic vs. full facilities)
  • Special features (cranes, compressed air, etc.)

Phase 2: Site Analysis and Zoning Research (Week 3-4)

The Gig Harbor Setback Crisis

The Problem: A client designed their dream 50x80 barn before checking local regulations. Pierce County's rural setback requirements meant the building had to be 75 feet from any property line - impossible on their 2-acre lot.

The Solution: We redesigned as a 40x60 building positioned to meet setbacks while adding a 20x40 lean-to later for the same total space.

Lesson Learned: Always research restrictions before finalizing design.

Zoning Research Checklist

Setback Requirements:

  • Distance from property lines (front, side, rear)
  • Distance from existing structures
  • Distance from wells, septic systems, or wetlands
  • Special requirements for corner lots or waterfront properties

Height and Size Restrictions:

  • Maximum building height
  • Maximum coverage percentage of lot
  • Maximum square footage for accessory buildings
  • Restrictions on commercial use in residential zones

Use Restrictions:

  • Permitted vs. conditional uses
  • Home business regulations
  • Environmental restrictions
  • Historic district requirements

Phase 3: Site Evaluation and Engineering (Week 5-6)

The Yelm Soil Surprise

Unexpected Challenge: A simple horse barn project hit 3 feet of peat bog under what appeared to be solid ground. Standard post-frame construction wouldn't work.

Our Solution: Concrete piers down to the gravel layer with post-frame structure above grade. Added $8,000 to the project but prevented future settling issues.

Key Point: Site evaluation before design saves money compared to design changes during construction.

Professional Site Evaluation

Soil Assessment:

  • Soil type and bearing capacity
  • Drainage characteristics
  • Seasonal water table levels
  • Presence of rock, sand, clay, or organic materials

Topographic Analysis:

  • Natural drainage patterns
  • Required grading and excavation
  • Access routes for construction
  • Views and solar orientation

Utility Assessment:

  • Distance to electrical service
  • Water and septic system locations
  • Internet and phone service availability
  • Propane or natural gas access

Phase 4: Design Development (Week 7-10)

The Tacoma Workshop Evolution

Initial Request: "We need a 30x40 workshop."

Final Design: 36x48 workshop with 12x36 lean-to, office area, and customer parking.

Design Process:

  1. Function mapping: Identified workflow patterns and space needs
  2. Equipment planning: Sized spaces for current and planned equipment
  3. Traffic analysis: Separated customer and work areas
  4. Growth accommodation: Designed for lean-to addition
  5. Code compliance: Met commercial workshop requirements

Result: Building that functions better than initially envisioned while meeting all regulatory requirements.

Design Development Process

Functional Layout:

  • Work area sizing and configuration
  • Traffic flow patterns
  • Storage requirements and locations
  • Separation of different functions

Structural Design:

  • Building dimensions and height
  • Door and window locations
  • Load requirements (equipment, storage, snow)
  • Foundation type and specifications

Systems Integration:

  • Electrical load calculations and panel location
  • Plumbing rough-in requirements
  • HVAC planning and equipment sizing
  • Internet/phone infrastructure

Phase 5: Budget Development (Week 11-12)

Real Project Budgets

Olympia 30x40 Workshop (2024):

  • Basic structure: $38,000
  • Concrete floor: $4,500
  • Electrical service: $3,200
  • Insulation package: $2,800
  • Site preparation: $1,800
  • Permits and fees: $1,200
  • Total: $51,500

Lakewood 40x60 RV Garage (2024):

  • Basic structure: $58,000
  • 16-foot height: $3,500
  • Large overhead door (14x16): $2,800
  • Concrete floor: $7,200
  • Electrical service: $4,200
  • Site preparation: $2,900
  • Permits and fees: $1,800
  • Total: $80,400

Budget Categories and Planning

Base Building Costs (70-75% of budget):

  • Posts, trusses, and framing
  • Roofing and siding materials
  • Doors and windows
  • Basic labor and installation

Site Work (10-15% of budget):

  • Excavation and grading
  • Foundation or concrete work
  • Driveway and access improvements
  • Drainage systems

Systems and Upgrades (10-15% of budget):

  • Electrical service and wiring
  • Plumbing installation
  • Insulation and interior finishing
  • Special features or equipment

Permits and Professional Services (3-5% of budget):

  • Building permits and inspections
  • Engineering and design fees
  • Surveying if required
  • Utility connection fees

Success Metrics: What Good Planning Achieves

Project Outcomes We Track

Timeline Performance:

  • Well-planned projects: 98% complete within 1 week of schedule
  • Poorly planned projects: 60% complete within 4 weeks of schedule

Budget Performance:

  • Well-planned projects: 95% within 5% of final budget
  • Poorly planned projects: 40% exceed budget by 15%+

Client Satisfaction:

  • Projects with thorough planning: 98% client satisfaction
  • Projects with minimal planning: 70% client satisfaction

Common Planning Mistakes and How to Avoid Them

Mistake 1: Underestimating Site Complexity

Example: A Federal Way client planned a simple 30x40 garage. During construction, we discovered underground utilities, poor drainage, and protected trees - adding 6 weeks and $12,000.

Prevention: Professional site evaluation before design finalization.

Mistake 2: Inadequate Electrical Planning

Example: A Tacoma workshop was designed with basic electrical, but the client's equipment required 220V service throughout. Retrofitting added $8,000.

Prevention: Equipment load analysis during design phase.

Mistake 3: Permit Surprises

Example: A rural Pierce County barn triggered environmental review due to seasonal creek proximity, delaying the project 8 weeks.

Prevention: Early consultation with building department.

Regional Planning Considerations

Pierce County Specifics

  • Rural areas: Environmental review for critical areas
  • Soil conditions: Marine clay requires deeper foundations
  • Permit timelines: 4-6 weeks for standard projects
  • Setback requirements: Vary significantly by zoning

King County Considerations

  • Urban areas: Design review for aesthetics
  • Environmental sensitivity: Steep slope and wetland regulations
  • Permit complexity: More detailed review process
  • Utility requirements: Higher connection standards

Thurston County Factors

  • Agricultural zoning: Opportunities for larger buildings
  • Flood zones: FEMA requirements near rivers
  • Historic districts: Design compatibility requirements
  • Growth management: Urban vs. rural development rules

Planning Tools and Resources

Essential Documentation

  • Property survey: Boundary and easement information
  • Soil report: Professional analysis for larger projects
  • Utility maps: Location of existing services
  • Zoning information: Current use and restrictions

Professional Consultations

  • Architect or designer: For complex or specialized buildings
  • Structural engineer: For unusual loads or conditions
  • Surveyor: For boundary or elevation questions
  • Environmental consultant: For sensitive areas

Ready to Start Planning Your Project?

Successful post-frame building projects don't happen by accident. They result from thorough planning that addresses every aspect of your project before construction begins. While this process takes time upfront, it prevents costly delays, changes, and disappointments later.

Whether you're planning a simple storage building or a complex commercial facility, following this systematic approach ensures your project succeeds. Every successful project we've completed started with proper planning - and every problem project we've rescued suffered from inadequate planning.

Ready to start planning your post-frame building project? Call (253) 434-0550 for your free planning consultation. We'll guide you through this process step-by-step, helping you avoid common pitfalls while creating a building that serves your needs perfectly.

Contact us today to begin your project planning process, or browse our completed projects gallery to see examples of well-planned post-frame buildings throughout Western Washington.

Share this article

Help others discover this article

Share this article with your network to help spread the word.